Wynford Drive
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Rehabilitation Works at Wynford Drive and East Don River Bridges
What Work is Taking Place?
The East Don River and Wynford Drive Bridges will be rehabilitated as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement and repairs to the abutments and beams to both bridges. Read more »
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
The construction liaison committee meeting of Brentcliffe - Victoria Park for June 14, 2018. You can see the presentation here:
Hydro Duct Bank Connection Works for Science Centre Station between Wynford and Eglinton on Don Mills Road
What Work is Taking Place?
As part of ongoing utility relocation work for the future Science Centre Station, crews will be conducting hydro infrastructure work in the vicinity of the Don Mills Road and Eglinton Avenue East intersection, beginning as soon as Wednesday, June 13, 2018. Ongoing hydro infrastructure upgrades support construction of the Eglinton Crosstown LRT. Read more »
Wynford Drive Bridge Rehabilitation - Upcoming Work and Construction Staging: June 2018
Originally Published: June 8, 2018
Updated: June 16, 2018
What Work is Taking Place?
The Wynford Drive Bridge will be rehabilitated as part of the construction of the Eglinton Crosstown LRT. Bridge deck replacement and associated works will be performed to accommodate utility upgrades and the new LRT tracks and guideway in the center of Eglinton Avenue East. Read more »
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
The presentation for the construction liaison committee meeting of Brentcliffe - Victoria Park for the month of May 2018 can be viewed here:
REISSUE: LOW WATER PRESSURE NOTICE: Watermain Connection Work for Science Centre Station
What Work is Taking Place?
Crews are working to replace an existing watermain north of Eglinton Avenue East within the existing work zone at the northeast corner of Don Mills Road and Eglinton Avenue East. This work supports the upgrade of existing water infrastructure around the future Science Centre Station. Read more »
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting
The construction liaison committee meeting of Brentcliffe - Victoria Park was held on April 5, 2018. You can see the presentation here:
Central-East Open House (Laird Station to West At-Grade (Sunnybrook - O'Connor Stops)
Thank you for attending the open house about Laird Station to West At-Grade (Sunnybrook - O'Connor Stops) on March 28, 2018.
For those of you who missed it, the presentation is here: Read more »
Clearing, Grubbing, and Pruning between Don Avon Drive to Victoria Park Avenue in Preparation for Construction of Surface Stops
As our constructors get ready to ramp up construction activity at the surface section of the Eglinton Crosstown LRT project, clearing, grubbing, and pruning and protection activity continues as part of preparatory work. This activity commenced two years ago and is done on an ongoing, as-needed basis to support the construction of the Eglinton Crosstown Light Rail Transit Project (ECLRT). All works will be carried out with the approvals and cooperation of the responsible authority. Read more »
Bell Utility Relocations Between Gervais Dr & Victoria Park Ave
What Work is Taking Place?
The Eglinton roadway is changing as work continues to prepare for the construction of the surface section of the Eglinton Crosstown LRT that will run down the centre of Eglinton Avenue East in dedicated transit lanes at street level. Setting up the construction work zones in the roadway will require changes to how car and truck, bus, and pedestrian traffic flows along Eglinton Avenue East and the associated intersections where future stops will be l Read more »