November 262018

Updated Pedestrian Routes at Wynford Drive Bridge

What Work is Taking Place?

As part of utility relocation and bridge rehabilitation works, new traffic staging was implemented between the Don Valley Parkway off-ramps and Wynford Drive early November, 2018.

An update to pedestrian routes will take effect as early as Wednesday, November 28th, 2018. The north-south crossing that was temporarily installed at Wynford Drive will be removed. The nearest pedestrian crossing will be located at the Don Valley Parkway North ramp.  Read more »

November 142018

Overnight Generator at Wynford Drive Bridge

What Work is Taking Place?

Crews continue the rehabilitation the Wynford Drive Bridge as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement and repairs to the abutments and beams to the bridge. Bridge rehabilitation works require traffic on Eglinton Avenue East to be shifted to the north side of Eglinton Avenue East to allow work to proceed on the south side.   Read more »

November 142018

Eastern Works Open House (Science Centre Station and Sunnybrook Park Stop to O'Connor Stop)

Thank you for attending the open house about Science Centre Station and Sunnybrook Park Stop to O'Connor Stop on November 13, 2018. For those of you who missed it, the presentation is here:

Read more »

November 132018

Traffic Change at East Don River Bridge

Originally Published: November 13, 2018

Last Updated: November 29, 2018

What Work is Taking Place?

The East Don River Bridge is being rehabilitated as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement and repairs to the abutments and beams to both bridges. Read more »

November 022018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here: Read more »

October 312018

Traffic Change at Don Valley Parkway Ramp to Wynford Drive Bridge

What Work is Taking Place?

A new traffic staging will be implemented between the Don Valley Parkway off-ramps and Wynford Drive Bridge as part of utility relocation works (depicted below), as early as November 4th. Read more »

October 152018

Watermain, Storm, and Sanitary Relocation at Eglinton Avenue East and Swift Drive Intersection

What Work is Taking Place?

As part of the construction of the future surface area stops, crews continue to upgrade and relocate wet utilities along Eglinton Avenue East between Credit Union Drive and Swift Drive.

In an effort to minimize disruption and to protect the safety of the local community and commuters, work will be performed overnight beginning as early as Monday, October 22nd, 2018 and last for approximately two (2) weeks. Read more »

October 042018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here:

Read more »

September 192018

Temporary Traffic Changes at East Don River Bridge to Facilitate Early Morning Deck Pour

What Work is Taking Place?

The East Don River and Wynford Drive Bridges are being rehabilitated as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement, and repairs to the supports and beams to both bridges.

As part of the ongoing works crews will be conducting deck pouring at the East Don River Bridge. This work is scheduled to start as early as Saturday, September 22nd  — to facilitate this work there will be a temporary traffic staging. Read more »

September 112018

Large Deliveries at East Don River Bridge

What Work is Taking Place?

The East Don River and Wynford Drive Bridges are currently being rehabilitated as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement and repairs to the abutments and beams to both bridges.

To facilitate the safe and timely delivery of steel plates for girders to the construction sites for the East Don River Bridge, starting as early as Wednesday, September 12, 2018 at 11 AM. Traffic interruptions can be expected while this delivery takes place. Read more »