Wynford Drive
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Updated Pedestrian Routes at Wynford Drive Bridge
What Work is Taking Place?
As part of utility relocation and bridge rehabilitation works, new traffic staging was implemented between the Don Valley Parkway off-ramps and Wynford Drive early November, 2018.
An update to pedestrian routes will take effect as early as Wednesday, November 28th, 2018. The north-south crossing that was temporarily installed at Wynford Drive will be removed. The nearest pedestrian crossing will be located at the Don Valley Parkway North ramp. Read more »
Overnight Generator at Wynford Drive Bridge
What Work is Taking Place?
Crews continue the rehabilitation the Wynford Drive Bridge as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement and repairs to the abutments and beams to the bridge. Bridge rehabilitation works require traffic on Eglinton Avenue East to be shifted to the north side of Eglinton Avenue East to allow work to proceed on the south side. Read more »
Eastern Works Open House (Science Centre Station and Sunnybrook Park Stop to O'Connor Stop)
Thank you for attending the open house about Science Centre Station and Sunnybrook Park Stop to O'Connor Stop on November 13, 2018. For those of you who missed it, the presentation is here:
Traffic Change at East Don River Bridge
Originally Published: November 13, 2018
Last Updated: November 29, 2018
What Work is Taking Place?
The East Don River Bridge is being rehabilitated as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement and repairs to the abutments and beams to both bridges. Read more »
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here: Read more »
Traffic Change at Don Valley Parkway Ramp to Wynford Drive Bridge
What Work is Taking Place?
A new traffic staging will be implemented between the Don Valley Parkway off-ramps and Wynford Drive Bridge as part of utility relocation works (depicted below), as early as November 4th. Read more »
Watermain, Storm, and Sanitary Relocation at Eglinton Avenue East and Swift Drive Intersection
What Work is Taking Place?
As part of the construction of the future surface area stops, crews continue to upgrade and relocate wet utilities along Eglinton Avenue East between Credit Union Drive and Swift Drive.
In an effort to minimize disruption and to protect the safety of the local community and commuters, work will be performed overnight beginning as early as Monday, October 22nd, 2018 and last for approximately two (2) weeks. Read more »
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here:
Temporary Traffic Changes at East Don River Bridge to Facilitate Early Morning Deck Pour
What Work is Taking Place?
The East Don River and Wynford Drive Bridges are being rehabilitated as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement, and repairs to the supports and beams to both bridges.
As part of the ongoing works crews will be conducting deck pouring at the East Don River Bridge. This work is scheduled to start as early as Saturday, September 22nd — to facilitate this work there will be a temporary traffic staging. Read more »
Large Deliveries at East Don River Bridge
What Work is Taking Place?
The East Don River and Wynford Drive Bridges are currently being rehabilitated as part of the construction of the Eglinton Crosstown LRT. Works include deck replacement, reinforcement and repairs to the abutments and beams to both bridges.
To facilitate the safe and timely delivery of steel plates for girders to the construction sites for the East Don River Bridge, starting as early as Wednesday, September 12, 2018 at 11 AM. Traffic interruptions can be expected while this delivery takes place. Read more »