Warden Avenue
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Upcoming Crane and Building Delivery of TPSS 11 - Monday November 25 – Thursday November 28, 2019
What Work is Taking Place
The Traction Power Substation 11 (TPSS 11) building will be delivered to Scarborough Nissan on Monday November 25, 2019. The TPSS 11 will be delivered in three oversized loads. Vehicles carrying the loads will travel southbound on Warden Avenue and continue eastbound on Civic Road.
Traffic will be temporarily stopped south of Civic Road in both directions to accommodate the delivery. Read more »
UPDATED: EXTENSION OF OVERNIGHT WORK AT WARDEN AVENUE
Original Post: October 22, 2019
Updated: October 31, 2019
WHAT WORK IS TAKING PLACE?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will work extended hours at the Traction Power Substation 11, located on the southeast side of Eglinton Avenue East and Warden Avenue. As early as Wednesday, October 23, 2019 work will take place between the hours of 7:00 p.m. to 5:00 a.m. Due to bad weather, overnight work at Warden will continue until Friday, November 8. Read more »
Eastern Works Open House
Thank you for attending the Easterm Works Open House on October 24, 2019. For those of you who missed it, the presentation is here:
Pharmacy to Kennedy Construction Liaison Committee Meeting
The construction liaison committee meeting of Pharmacy to Kennedy was held on September 24, 2019. You can see the presentation here:
Construction for TPSS (Traction Power Substation) 11 Begins
CONSTRUCTION BEGINS FOR TPSS 11:
Eglinton Avenue East at Warden Avenue
What Work is Taking Place? Read more »
UPDATE: CHANGE OF DATES Weekend Paving and Guideway Work at Warden Avenue
WHAT WORK IS TAKING PLACE?
As part of the ongoing pavement reconstruction works at intersections along Eglinton Avenue East in support of construction of the future surface stops, crews will be conducting pavement reconstruction works at the Warden Avenue and Eglinton Avenue East intersection. Work began in November 2018 and will continue on Friday August 2 and Saturday August 3, with intersection traffic restriction on the north side of Warden Avenue.
Guideway Work at Warden Avenue
What Work is Taking Place?
As part of the ongoing pavement reconstruction works at intersections along Eglinton Avenue East in support of construction of the future surface stops, crews will be conducting pavement reconstruction works at Warden intersection at Eglinton Avenue East. As early as July 29, 2019 the construction zone will shift to the center of Eglinton Avenue East at Warden Avenue and be in place for approximately six (6) weeks. There will be no through north-south traffic on Warden and left turn restrictions at the intersection. Read more »
UPDATED: Duct Bank installation at Warden Avenue for TPSS 11
What Work Is Taking Place?
Work on the southeast corner of Warden Ave and Eglinton Ave E will start as early as July 8th, 2019 to support the upcoming construction of Traction Power Substation (TPSS) 11 that will power the Eglinton Crosstown Light Rail Transit (ECLRT) line.
This work will be ongoing until the end of July 2019.
Crews will continue excavating, installing, and pouring concrete for duct banks at the south east corner of the Warden intersection. Read more »