Victoria Park Avenue

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
October 292018

Paving at Eglinton Square

What Work is Taking Place?

Crews will begin the first series of grading and paving operations at Eglinton Square, south of Eglinton Avenue East as part of the construction of the future O’Connor Stop under the Eglinton Crosstown LRT Project. Work is expected to begin as early as Tuesday, October 30, 2018. Read more »

October 042018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here:

Read more »

September 172018

Update: New Traffic Changes from Victoria Park Avenue to Birchmount Road to Support Surface Section Work

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting traffic changes in order to accommodate road widening, upgrading and relocating wet utilities and dry utilities along Victoria Park Avenue to Birchmount Road starting as early as Friday, September 21st.

Preparatory work for the reconfiguration will take place as early as Friday, September 21, 2018 starting at 7:00 PM and ending Monday, September 24, 2018 at 6:00 AM. Read more »

September 142018

New Traffic Changes from Victoria Park Avenue to Birchmount Road to Support Surface Section Work

Originally Published: September 14, 2018

Updated: September 17, 2018

As work intensifies along the surface portion of the Eglinton Crosstown Light Rail Transit Project in preparation for guideway construction, there will be some major changes.

Expect to see new traffic changes between Victoria Park and Birchmount beginning less than a week from today — as early as Friday, September 21, 2018. Read more »

September 132018

Rolling Sidewalk Closures for Civil Road Work from Victoria Park Avenue to Pharmacy Road

Originally Published: September 13, 2018

Last Updated: December 14, 2018

What Work is Taking Place?

In support of construction of the future At Grade stops, crews will be conducting civil works in relation to Road Widening works on both the north and south sides of Eglinton Avenue East between Victoria Park Avenue and Pharmacy Avenue. Read more »

August 242018

Construction Notice: New Street Light Installation and Civil Work on Eglinton Ave E starting August 27, 2018

What Work is Taking Place?

In support of construction of the future At Grade stops, crews will be conducting new street light installation and civil works on Eglinton Avenue East between Victoria Park Avenue and Pharmacy Avenue starting as early as Monday, August 27th, 2018 with an anticipated completion date of December 2018. Read more »

August 172018

Wet Utility Upgrades along Surface Section of the Eglinton Crosstown LRT: Victoria Park Avenue to Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be upgrading and relocating wet utilities in the center of Eglinton Avenue East between Victoria Park Avenue and Birchmount Road starting as early as Monday, August 20th, 2018. Read more »

July 032018

Wet Utility Upgrades along Surface Section of the Eglinton Crosstown LRT: Victoria Park to Eglinton Square

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be upgrading and relocating wet utilities along Eglinton Avenue between Victoria Park Avenue and Eglinton Square.

Starting as early as July 3rd and lasting approximately four (4) weeks, crews will install new pipes, and replace manholes and catch basins. This work supports the upgrade of water infrastructure across Eglinton Avenue East for the future Crosstown surface stops. Read more »

June 252018

Reissue: Hydro Utility Relocation between Bermondsey and Birchmount for the Eglinton Crosstown LRT

 

What Work is Taking Place?

The Eglinton roadway is changing as work continues to prepare for the construction of the surface section of the Eglinton Crosstown LRT that will run down the centre of Eglinton Avenue East in dedicated transit lanes at street level.

Setting up the construction work zones in the roadway will require changes to how car and truck, bus, and pedestrian traffic flows along Eglinton Avenue East and the associated intersections where future stops will be located.  Read more »