September 9, 2020

September 21, 2020

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the O'Connor Stop north and south platform. North platform installation will begin as early as September 21, 2020 for approximately three days and the south platform will follow for approximately three days. 

What to Expect

A crane will be installed within the guideway work zone to facilitate shelter installation. The structures will be delivered and lifted into place by the crane. Concrete works will also take place as part of shelter installation. Daily lane closures will be required at the work zone.

Traffic and Pedestrian Details

  • Westbound traffic will be restricted to one lane between Victoria Park and Eglinton Square for the north shelter installation.
  • Eastbound traffic will be restricted to one lane between Victoria Park and Eglinton Square for the south shelter installation.
  • There will no changes to existing pedestrian routes at the intersection.

Hours of Work

  • Work will begin as early as September 21, 2020 and continue for approximately one week.  
  • Work may occur from 7:00 a.m. to 11:00 p.m., seven (7) days per week, Monday through Sunday.
  • Work may be rescheduled due to unforeseen circumstances.

Other Information  

  • Due to the nature of this work, at times there will be noise around the work area.

 

Disponible en français.