Pharmacy Avenue
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Track Slab Concrete Pour of Guideway at Eglinton Square - April 3, 3019
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the centre of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »
Track Slab Concrete Pour of Guideway- Eglinton Square - April 5 & April 6, 2019
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »
Extended: Sidewalk Closure for Civil Road Work between Pharmacy Avenue and Lebovic Avenue
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting civil road work in relation to road widening works on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue. Work began in February 2019 and will be extended until the end of April 2019.
There will be sidewalk closure on the south side of Eglinton Avenue East between Pharmacy Avenue and Lebovic Avenue in order to safely carry out the work.
Hours of Work Read more »
Driveway Access Restrictions for Civil Road Work
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing civil road work in relation to road widening and curb relocation activities on the south side of Eglinton Avenue East between Pharmacy Avenue and Hakimi Avenue. Read more »
Pharmacy to Kennedy Construction Liaison Committee Meeting
The construction liaison committee meeting of Pharmacy to Kennedy was held on March 26, 2019. You can see the presentation here:
Overnight Utilities Relocations at Pharmacy Avenue and Eglinton Avenue East
WHAT WORK IS TAKING PLACE?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews continue to relocate and upgrade existing overhead and underground telecommunication between Victoria Park Avenue and Birchmount Road. Read more »
Weekend Intersection Paving Traffic Restriction at Pharmacy Avenue
Latest Update: March 27, 2019
What Work is Taking Place?
As part of the ongoing pavement reconstruction works at intersections along Eglinton Avenue East between Victoria Park Avenue and Birchmount Road in support of construction of the future surface stops, crews will be conducting pavement reconstruction works at the Pharmacy Avenue intersection along Eglinton Avenue East. Read more »
Duct Bank Concrete Pour of Guideway- Eglinton Square to Pharmacy Avenue
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »
Updated: Lane Reductions to facilitate Civil Road Work at the South East Corner of Pharmacy Intersection
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing civil road work activities along Eglinton Avenue East. Starting as early as Monday, March 18 and lasting for approximately twelve (12) days, crews will be conducting curb installation at the south-east corner of Pharmacy Avenue and Eglinton Avenue East.
In order to facilitate this work, there will be temporary lane reduction at the south east corner of Pharmacy Avenue. Read more »
Duct Bank Concrete Pour of Guideway- Eglinton Square to Pharmacy Avenue
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue. Read more »