Pharmacy Avenue
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Permanent Westbound Left Turn Lane Removal – Pharmacy Avenue
What Work is Taking Place?
In order to accommodate the future Pharmacy Stop construction, the westbound left turn lane (to southbound) will be removed at the Pharmacy Avenue and Eglinton Avenue East intersection as early as September 16, 2019. Read more »
Pharmacy to Kennedy Construction Liaison Committee Meeting
The construction liaison committee meeting of Pharmacy to Kennedy was held on May 28, 2019. You can see the presentation here:
Track Slab Concrete Pour of Guideway- Eglinton Square
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East between Eglinton Square and Pharmacy Avenue.
Crews will be delivering and pouring cement along Eglinton Avenue East between Eglinton Square and Pharmacy Avenue as early as Wednesday May 15 from 7:00 a.m. until 7:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west of Eglinton Avenue East. Read more »
Concrete Pour of Guideway- Pharmacy Avenue Intersection May 11, 2019
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East at the Pharmacy Avenue intersection.
Crews will be delivering and pouring cement along Eglinton Avenue East at the Pharmacy intersection as early as Saturday May 11, 2019 from 7:30 a.m. until 7:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west of Eglinton Avenue East. Read more »
Pharmacy to Kennedy Construction Liaison Committee Meeting
The construction liaison committee meeting of Eglinton and Mount Pleasant stations was held on April 30, 2019. You can see the presentation here:
Guideway Work along Surface Section of the Eglinton Crosstown LRT: Pharmacy Avenue at Eglinton Avenue East
Latest Update: April 23, 2019
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the center of Eglinton Avenue East between Victoria Park Avenue and Pharmacy Avenue. Starting as early as May 1, 2019 for approximately six (6) weeks.
The work includes cutting and removal of existing asphalt, excavation, installation of subgrade materials, duct banks installation and track drainage, track slab and stops. Read more »
Eastern Works Open House
Thank you for attending the Eastern Work Open House on April 10, 2019. For those of you who missed it, the presentation is here:
Sidewalk Closure for Civil Road Work between Pharmacy Avenue and Hakimi Avenue
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting civil road work in relation to road widening works on the north side of Eglinton Avenue East between Pharmacy Avenue and Hakimi Avenue. Starting as early as April 19th and lasting for approximately one (1) month there will be a sidewalk closure on the north side of Eglinton Avenue East, between Pharmacy Avenue and Hakimi Avenue in order to safely carry out the work. Read more »
Lane Reductions to facilitate Civil Road Work at the North East Corner of Pharmacy Intersection
What Work is Taking Place?
As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing civil road work activities along Eglinton Avenue East. Starting as early as Monday, April 8 and lasting for approximately five (5) days, crews will be conducting curb installation at the north east corner of Pharmacy Avenue and Eglinton Avenue East.
In order to facilitate this work, there will be temporary lane reductions at north east corner of Pharmacy Avenue. Read more »