Mount Pleasant Road

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
September 252020

UPDATED: Notice of Planned Water Shut-off and Overnight Watermain Connection Work at Mount Pleasant Station

Original Post: September 22, 2020

Updated: September 23 & 25, 2020

 

 

What Work is Taking Place? Read more »

September 112020

Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - September 14, 2020

 

What Work is Taking Place?

As early as Monday September 14, 2020, crews at Mount Pleasant Station will perform a concrete pour within the work zone of the north side of Eglinton Avenue East, west of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 7:00 a.m. and take approximately five (5) hours to complete. Read more »

September 112020

Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - September 14, 2020

 

What Work is Taking Place?

As early as Monday September 14, 2020, crews at Mount Pleasant Station will perform a concrete pour within the work zone of the north side of Eglinton Avenue East, west of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 7:00 a.m. and take approximately five (5) hours to complete. Read more »

September 102020

Eglinton & Mount Pleasant Construction Liaison Committee Meeting

Construction Liaison Committee of Eglinton and Mt Pleasant was held on September 9, 2020. You can see the presentation here:

 

Read more »

September 042020

Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - September 8, 2020

 

 

What Work is Taking Place?

As early as Tuesday September 8, 2020, crews at Mount Pleasant Station will perform a concrete pour within the work zone of the north side of Eglinton Avenue East, west of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 5:00 a.m. and take approximately eighteen (18) hours to complete. Read more »

September 022020

Jersey Barrier Installation at Mount Pleasant Road and Eglinton Avenue East - Thursday September 3, 2020

 

What Work is Taking Place?

On Thursday September 3, 2020 crews at Mount Pleasant Station will install jersey barriers along the south sidewalk of Eglinton Avenue East, between Mount Pleasant Road and Brownlow Avenue. Using a forklift, crews will place the jersey barriers along the curb of the sidewalk, to delineate pedestrians from traffic and constriction. Read more »

September 022020

UPDATED: Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - September 3, 2020

 

Original Post: August 31, 2020

Updated on September 2, 2020

 

What Work is Taking Place?

As early as Thursday September 3, 2020, crews at Mount Pleasant Station will perform a concrete pour within the  Secondary Entrance site. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 6:00 a.m. and take approximately twelve (12) hours to complete. Read more »

August 262020

Sidewalk Restoration Work at Mount Pleasant Road and Eglinton Avenue East -Thursday August 27, 2020

 

As early as Thursday August 27, crews at Mount Pleasant Station will perform restoration work on the south sidewalk of Eglinton Avenue East, between Mount Pleasant Road and Brownlow Avenue. This work will begin as early as 8:00 p.m. and take approximately three (3) hours to complete.  Read more »

August 142020

Upcoming Concrete Pour at Mount Pleasant Road and Eglinton Avenue East - Monday August 17, 2020

 

 

What Work is Taking Place?

As early as Monday August 17, 2020 crews at Mount Pleasant Station will perform a concrete pour within the work zone of the north side of Eglinton Avenue East, west of Mount Pleasant Road. The concrete will form one of the permanent station structures underground. To ensure the integrity and continuity of the pour, work will begin as early as 7:00 a.m. and take approximately five (5) hours to complete.

August 112020

Concrete Pours at Mt Pleasant Road and Eglinton Avenue East - Wednesday August 12, 2020

 

As early as Wednesday August 12, 2020, crews at Mount Pleasant Station will perform concrete pours within the main and secondary entrances on the north side of Eglinton Avenue East. The concrete will form one of the permanent station structures underground. Work will begin at approximately 8:00 a.m. and is expected to take six (6) hours to complete. 

  Read more »