Laird Station Concrete Pour - September 10, 2020
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
September 10, 2020
What Work is Taking Place?
Beginning September 10, 2020, crews will perform a concrete pour at the main entrance at Laird Station. Preparatory work may begin as early as 6:00 a.m., the pour will take place between the hours of 7:00 a.m. and 11:00 p.m.
What to Expect
A concrete pour will take place at the main entrance of Laird station. Because concrete pours require a continuous supply of concrete, there will be a truck staging area set-up that will occupy one southbound lane on Laird Drive, south of Eglinton Ave East. Noise can be expected from concrete trucks and pumps.
In the event of inclement weather, this work may be rescheduled
Hours of Work
- The concrete pour will take place on Thursday, September 10, 2020.
- Preparatory work may begin as early as 6:00 a.m., the pour will take place between the hours of 7:00 a.m. and 11:00 p.m.
- In the event of inclement weather, this work may be rescheduled.
Traffic and Pedestrian Details
- A temporary closure of one southbound lane on Laird Drive south of Eglinton Avenue East.
- Increased truck traffic travelling through the area can be expected.
- There will be no changes to existing pedestrian routes.
TTC Information
- There will be no changes to existing TTC stop locations for this pour.
Other Information
- Noise can be expected from concrete trucks and pumps.
- Site lighting may be required.