CONCRETE POUR AT LAIRD STATION

May 27, 2020

On May 27, 2020, crews will perform a concrete pour at the main entrance of Laird Station. Work will begin as early as 5:00 a.m. and the pour will be ongoing until approximately 11:00 p.m. Laird Avenue and Eglinton Avenue East will remain open while work takes place.


WHAT TO EXPECT

  • Four trucks will be staged at a time at the main entrance site.
  • Because concrete pours require continuous supply of concrete, truck staging area will occupy one southbound lane on Laird Drive.
  • Noise can be expected from concrete trucks and pumps.

HOURS OF WORK

  • As early as May 27, 2020 for one (1) day.
  • The concrete pour will begin at 5:00 a.m. and continue until 11:00 p.m.
  • In the event of inclement weather, this work may be rescheduled.

TRAFFIC IMPACTS

  • A temporary closure of one southbound lane on Laird Drive south of Eglinton Avenue East.
  • Traffic control personnel and a paid duty officer will be present while this work takes place.
  • Increased truck traffic travelling through the area.

PEDESTRIAN AND TTC IMPACTS

  • There will be no new impacts to existing pedestrian routes or TTC stops.