Chaplin Crescent

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
April 072022

Extended: Chaplin Crescent Closure for Utility and Road Restoration Works - Until mid April 2022

 

 

What Work is Taking Place?

Chaplin Crescent will remain closed between Eglinton Avenue West and the Chaplin-Russel Hill laneway until mid-April 2022, as crews continue road and sidewalk restoration works . Eglinton Avenue West will remain open. Significant traffic changes will be in effect. Please carefully read the details below.

March 242022

Laneway Closure at Chaplin Station - Through April 2022

What Work is Taking Place?

The laneway located between Chaplin Crescent and Russell Hill Road, south of Eglinton Avenue, will be remain closed through April 2022 to accommodate construction works for Chaplin Station's Tertiary Entrance building.

What to Expect Read more »

March 222022

Extended: Chaplin Crescent Closure for Utility and Road Restoration Works - Until early April 2022

What Work is Taking Place?

Chaplin Crescent will remain closed between Eglinton Avenue West and the Chaplin-Russel Hill laneway until early April 2022, as crews continue dry utility installations, and begin road and sidewalk restoration works at the intersection. Eglinton Avenue West will remain open. Significant traffic changes will be in effect. Please carefully read the details below.

March 022022

Avenue & Chaplin CLC - Presentation Deck - March 2, 2022

intro

The Construction Liaison Committee of Avenue & Chaplin was held on March 2, 2022. You can review the presentation here: Read more »

February 142022

Extended: Chaplin Crescent Closure for Pile Removals and Utility Works

Last updated: March 10, 2022

WHAT WORK IS TAKING PLACE?

Chaplin Crescent will remain closed between Eglinton Avenue West and the Chaplin-Russel Hill laneway until late March 2022, as crews continue pile removals and dry utility works at the intersection. Eglinton Avenue West will remain open. Significant traffic changes will be in effect. Please carefully read the details below.

January 072022

Chaplin Crescent Closure for Pile Removals and Utility Works - January 17, 2022

*Information updated on January 14, 2022*

Chaplin Crescent Closure for Pile Removals and Utility Works January 15, 2022

What Work is Taking Place?

January 062022

Avenue & Chaplin CLC - Presentation Deck - January 5, 2022

The Construction Liaison Committee of Avenue & Chaplin was held on January 5, 2022. You can review the presentation here:

Read more »

December 162021

UPDATE: Crane Removal at Chaplin Station - December 18-19, 2021

Update: Due to weather conditions, this work may be required to also take place on Sunday December 19, 2021. 

Crane Removal at Chaplin Station - December 18, 2021

What Work is Taking Place?