September 232020

Late Night Concrete Pour at Birchmount Road and Eglinton Avenue East - September 24, 2020

 

 

What Work is Taking Place?

On September 24, 2020, crews will perform a late-night concrete pour on Eglinton Avenue East, West of Birchmount Road. The concrete will form the plinths that will support the future tracks of the Eglinton Crosstown LRT.  The pour will take place between the hours of 10:00 p.m. and 3:00 a.m.  Read more »

September 142020

Birchmount Stop Permanent Left Turn Removal - September 15, 2020

 

What Work isTaking Place?

To accommodate the continued construction of Birchmount Stop and as part of the final intersection configuration, the eastbound left turn movement at Eglinton Avenue East and Birchmount Road will be permanently removed as early as September 15, 2020. 

The westbound left turn movement was removed permanently late 2019.

 

What to Expect Read more »

August 192020

Closure on Rosemount Drive North of Eglinton Avenue East - Extended to late October 2020

 

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended to late October 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through-traffic will be prohibited for the duration of the work. Read more »

August 142020

North and South Platform Shelter Installation at Birchmount Stop - August 24, 2020

 

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Birchmount Stop north and south platform. North platform installation will begin as early as August 24, 2020 for three days and the south platform will begin on August 27, 2020 for three days.  

 

What to Expect Read more »

July 292020

Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2020

Construction Liaison Committee of Pharmacy to Kennedy was held on July 28, 2020. You can see the presentation here:

 

Download the presentation

May 272020

Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020

Construction Liaison Committee of Pharmacy to Kennedy was held on May 26, 2020. You can see the presentation here:

May 272020

UPDATED: Closure on Rosemount Drive North of Eglinton Avenue East - Extended Until Mid August 2020

Original Post: March 24, 2020

Updated on May 27, 2020

 

What Work is Taking Place

As part of the ongoing works to replace the existing culvert at Massey Creek, the current traffic configuration at Rosemount Drive and Eglinton Avenue East will be extended until mid-August, 2020. Rosemount Drive will remain closed north of Eglinton Avenue East and north-south through traffic will be prohibited for the duration of the work. Read more »

May 212020

Temporary Pedestrian Detour - Rosemount Drive to Ionview Road

 

May 25, 2020

What Work is Taking Place

As part of the ongoing construction for the future surface alignment of the Eglinton Crosstown LRT, crews are performing boulevard restoration works on the north side of Eglinton Avenue East between Rosemount Drive and Ionview Road. 

  Read more »

May 042020

Boulevard Restoration Works at 2354-2356 & 2360 Eglinton Ave East

 

What Work is Taking Place?

As part of the ongoing construction for the future surface alignment of the Eglinton Crosstown LRT, crews will be performing boulevard restoration works on the north side of Eglinton Avenue East between Rosemount Drive and Ionview Road. Partial or full driveway closures may be required to perform grading works to align driveways with the new road surface on Eglinton Avenue East.

Driveways may be restricted partially or fully beginning May 6, 2020 for up to three (3) weeks.

  Read more »