Bayview Avenue
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street

Upcoming Utility Works at Leaside Station
Upcoming Utility Works at Leaside Station
What Work is Taking Place? Read more »
Update: Extended Construction Hours at Leaside Station - June 2021
Through Summer 2021, crews at Leaside Station will continue to work extended construction hours at the station entrances and in the station box below Eglinton Avenue. Construction activities include waterproofing, placement of rebar and steel, formwork installations, mechanical electrical works, and concrete pours.
Central East Crosstown Virtual Open House Presentation
Construction and progress updates for stations and stop including: Eglinton, Mount Pleasant, Leaside, Laird, Sunnybrook Park and Science Centre.
Upcoming Concrete Pour at Bayview Avenue and Eglinton Avenue East
As early as Wednesday April 14, 2021 crews at Leaside Station will perform a concrete pour at the Main Entrance site. The concrete will form the roof of Leaside Station’s Main Entrance building.
Fire Hydrant Removal at Eglinton Avenue East and Donlea Drive
From Wednesday March 31 – Thursday April 1, 2021, crews will work to remove an abandoned fire hydrant at the north-east corner of Eglinton Avenue East and Donlea Drive. This work is expected to take place between 7:00 a.m. – 3:00 p.m.
Fire Hydrant Removal at Eglinton Avenue East and Donlea Drive
From Wednesday March 31 – Monday, April 5, 2021, crews will work to remove an abandoned fire hydrant at the north-east corner of Eglinton Avenue East and Donlea Drive. This work is expected to take place between 7:00 a.m. – 3:00 p.m.
Scaffolding Installation at Leaside Station's Main Entrance -February 15 2021
As early as February 15, 2021, crews at Leaside Station will begin to install a temporary scaffolding system along the east wall of the Main Entrance site to provide overhead protection and delineation for the work zone. Scaffolding installation will take place within the work zone between 7:00 a.m. – 11:00 p.m. for approximately two (2) days. The scaffolding system will remain in place for approximately four (4) months.