Traffic Signal Installations at Mount Pleasant Station - October 27, 2022
What Work is Taking Place?
On Thursday, October 27, 2022, crews at Mount Pleasant Station will perform traffic signal installations at the intersection of Mount Pleasant Road and Eglinton Avenue East. Rolling lane closures are required to facilitate this work. Periodically, Eglinton Avenue East will be reduced to one lane only at the intersection, with traffic alternating in each direction. To mitigate impact to the traveling public, this work will take place during off-peak hours between 10:00 a.m. – 3:00 p.m. for approximately one (1) day.
What to Expect
Noise from construction activities, including material loading, hammering, and the use of a lift, can be expected. Expect delays while traveling through the intersection. Traffic control personnel and/or a Paid Duty Officer will be present while this work takes place.
HOURS OF WORK
TRAFFIC DETAILS
PEDESTRIAN DETAILS
TRANSIT INFORMATION