Concrete Pour of Guideway- Pharmacy Avenue Intersection May 11, 2019

 
mai 9, 2019

What Work is Taking Place?

As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East at the Pharmacy Avenue intersection.

Crews will be delivering and pouring cement along Eglinton Avenue East at the Pharmacy intersection as early as Saturday May 11, 2019 from 7:30 a.m. until 7:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west of Eglinton Avenue East.

Concrete Pour of Guideway at Pharmacy Ave
Hours of Work
  • Work is expected to start as early as Saturday, May 11, 2019 from 7:30 am until 7:00 pm.  
  • Work may be rescheduled due to weather conditions or unforeseen circumstances.
What to Expect
  • Heavy trucks entering and exiting the work zone (approximately every nine to ten (9-10) minutes).
  • Trucks will be entering and leaving the site at:
  • West of Eglinton Avenue East and will use the left lane to enter the stage
  • East of Eglinton Avenue East and will use the left lane to enter the stage
  • Flagmen will be available to direct traffic and pedestrians.
  • A minimum of one lane of traffic in each direction will be maintained during this work.
  • In addition to construction activity, residents and businesses can expect to see equipment and material storage within designated work zones.
  • As always, please take care when travelling near work.
Pedestrian Impacts
  • All open sidewalks and crosswalks will be maintained during this work.

 

Stay Informed