Updated: Concrete Pour of Guideway - East of Warden Avenue - April 22 & April 24, 2019
Originally Posted: April 15, 2019
Updated: April 18, 2019
What Work is Taking Place?
As part of continued support of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting a concrete pour of the guideway in the center of Eglinton Avenue East, just east of Warden Avenue and Thermos/Sinnott Road.
Crews will be delivering and pouring cement along Eglinton Avenue East just east of Warden Avenue and Thermos/Sinnott Road as early as Monday, April 22, 2019 AND Wednesday, April 24, 2019 from 7:30 a.m. until 7:00 p.m. To facilitate this delivery, concrete trucks will be arriving to the site from the east and west of Eglinton Avenue East

Hours of Work
- Work is expected to start as early as Monday, April 22, 2019 AND Wednesday, April 24, 2019 from 7:30 am until 7:00 pm.
- Work may be rescheduled due to weather conditions or unforeseen circumstances.
What to Expect
- Heavy truck entering and exiting the work zone (approximately every nine to ten (9-10) minutes).
- Trucks will be entering and leaving site:
- At the west of Eglinton Avenue East and will use the left lane to enter the stage
- At the east of Eglinton Avenue East and will use the left lane to enter the stage
- Flagmen will be available to direct traffic and pedestrians.
- A minimum of one (1) lane of traffic in each direction will be maintained during this work.
- In addition to construction activity, residents and businesses can expect to see equipment and material storage within designated work zones.
- As always, please take care when travelling near work zones.
Pedestrian Impacts
- All open sidewalks and crosswalks will be maintained during this work.
Stay Informed
Sign up for e-mail updates at http://www.thecrosstown.ca/sign-up or download the aCrosstown traffic app to get real-time traffic and transit information for the Eglinton corridor.
Disponible en Français