mai 132021

Light Rail Vehicle Delivery and Testing between Laird Dr. and Kennedy Rd.

 

East Testing and Commissioning Map

Starting May 25, six (6) Light Rail Vehicles (LRVs) will be moved from the Eglinton Maintenance and Storage Facility (EMSF) to the LRT tracks (guideway) at Rosemount Dr. via truck transport. The LRVs will be delivered one at a time, on May 25, 26, 27, 31 and June 1 and 2. 

  Lire la suite »

mai 062021

Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - May 6, 2021

Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.

Lire la suite »

avril 282021

Overnight OCS Cable Installations on Eglinton Avenue East between Don Mills Road and Sloane Avenue

Original Post: April 23, 2021

Updated: April 28, 2021 

Overnight OCS Cable Installations on Eglinton Avenue East between Don Mills Road and Sloane Avenue

WHAT WORK IS TAKING PLACE? Lire la suite »

octobre 082020

(Updated) Glazing Installation at Golden Mile, Birchmount, O'Connor and Wynford Stops

UPDATED OCTOBER 23, 2020

What Work is Taking Place?

Shelter installation has been ongoing across the surface alignment for the Eglinton Crosstown LRT, beginning October 26, 2020, crews will perform glazing installation at the Wynford, O'Connor, Golden Mile and Birchmount stop shelters.  Glazing consists of glass Installation works for the LRT shelters.

What to Expect Lire la suite »

octobre 012020

Duct Bank Installation at The West Don River Bridge

What Work is Taking Place?

Crews will begin installing duct banks under the West Don River Bridge as early as October 5, 2020. To perform this work safely, an alternating lane closure under the bridge will be in place for approximately six (6) weeks. Access to the E.T Seaton Park parking lot, south of Eglinton Avenue East will be maintained. There will be no impacts to traffic on Eglinton Avenue East.