Oakwood Avenue

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
septembre 032021

Fairbank & Oakwood Construction Update - September 2021

The following construction update for Fairbank and Oakwood stations has been updated as of September 1, 2021. You can view the presentation here: 

Lire la suite »

août 252021

Tower Crane Removal at Oakwood Station’s Main Entrance - August 27, 2021

What Work is Taking Place?

As early as Friday August 27, 2021, the tower crane at Oakwood Station’s Main Entrance will be dismantled and removed. A mobile crane will be placed at the Main Entrance site to lift out the tower crane in pieces. This work is expected to take place between 4:00 a.m. – 6:00 p.m. 

juillet 092021

CANCELLED: Wet Utility Connection Works at Oakwood Station: Phase One - August 9, 2021

*Information updated on July 30, 2021*
*Information updated on July 22, 2021*

Wet Utility Connection Works at Oakwood Station: Phase One July 19, 2021

What Work is Taking Place?

juillet 092021

Fairbank & Oakwood Construction Update - July 2021

The following construction update for Fairbank and Oakwood stations has been updated as of July 7, 2021. You can view the presentation here:

Lire la suite »

juin 072021

Concrete Pours at Oakwood Station - June 8 & 11, 2021

Concrete Pours at Oakwood Station June 8 & 11, 2021

What Work is Taking Place?

On Tuesday June 8 and Friday June 11, 2021, crews will perform a concrete pour within the work zone on the north side of Eglinton Avenue West at Oakwood Avenue. The concrete will form one of the exterior walls of Oakwood Station’s Main Entrance.

mai 312021

Concrete Pour at Oakwood Station - June 1, 2021

Concrete Pour at Oakwood Station June 1, 2021

What Work is Taking Place?

As early as Tuesday June 1, 2021, crews will perform a concrete pour within the work zone on the north side of Eglinton Avenue West at Oakwood Avenue. The concrete will form one of the exterior walls of Oakwood Station’s Main Entrance.