Leslie Street

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
août 202021

Noise Barrier Wall and Soil Nail Wall Removal

Rendering

 

As early as Fall 2021, crews will begin removing the temporary noise barrier wall and soil nail wall located on the south side of Eglinton Avenue East, east of Brentcliffe Rd. The temporary walls were erected in 2014 to facilitate the construction of the east portal. Removal of the walls will take approximately two (2) months. 

What to Expect Lire la suite »

juin 202021

OCS Cable Installations on Eglinton Avenue East between Laird Drive and Leslie Street

 

OCS Cable Installations on Eglinton Avenue East between Laird Drive and Leslie Street

What Work is Taking Place?

mai 132021

Light Rail Vehicle Delivery and Testing between Laird Dr. and Kennedy Rd.

 

East Testing and Commissioning Map

Starting May 25, six (6) Light Rail Vehicles (LRVs) will be moved from the Eglinton Maintenance and Storage Facility (EMSF) to the LRT tracks (guideway) at Rosemount Dr. via truck transport. The LRVs will be delivered one at a time, on May 25, 26, 27, 31 and June 1 and 2. 

  Lire la suite »

mai 062021

Brentcliffe to Victoria Park Construction Liaison Committee (CLC) Meeting - May 6, 2021

Construction updates for stations and stops including: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O'Connor.

Lire la suite »

mai 052021

Central East Crosstown Virtual Open House Presentation

Construction and progress updates for stations and stop including: Eglinton, Mount Pleasant, Leaside, Laird, Sunnybrook Park and Science Centre.

Lire la suite »

avril 302021

Overhead Catenary System Energization between Laird Drive and Kennedy Road

On May 3, 2021, the overhead catenary system (OCS) between Laird Drive and Kennedy Road will be energized. Once energized the OCS cables are electrified and dangerous if encountered. It is never safe to go near the OCS. Please obey signage and stay away from all overhead cables.

The OCS installed above the LRT tracks and powers the Light Rail Vehicles (LRVs). Power is delivered from traction power substations located along the alignment to the LRVs via the OCS cables. Lire la suite »

février 262021

Overnight OCS Cable Installation on Eglinton Ave at Laird, Leslie, Sloane & Kennedy. March 1 - April 2

 

What Work is Taking Place?

Crews will be installing OCS (Overhead Catenary System) cables along Eglinton avenue east between Laird drive, Leslie street, Swift drive, Sloane avenue, and Kennedy road. Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles). Lire la suite »