Laird Drive

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
juin 302017

Crane Installation at Laird Station Main Entrance

A large tower crane will be delivered and installed at the Laird Main Entrance during the week of July 3rd. 

What to Expect  Lire la suite »

juin 142017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on June 14, 2017. You can see the presentation here:

juin 062017

Gas Main Support at Laird Station

To prepare for upcoming mining operations at Laird Station, micro piles will be drilled to the north of the Laird Station Secondary entrance. Micro piles will support local gas mains during mining. 

Hours of Work/ What to Expect  Lire la suite »

juin 022017

Mining at Laird Station

The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Laird Station, are going to be “mined.” 

Excavation of the secondary entrance at Laird Station is complete and mining will begin soon.  Lire la suite »

mai 312017

Site Trailers and Crane Installation at Laird Station Secondary Entrance

Four site trailers and a crane will be delivered and installed at the Laird Station Secondary Entrance. 

Hours of Work  Lire la suite »

mai 122017

Update: Tunnel Concrete Pour for Laird Station

To progress construction at Laird Station and prepare for upcoming mining works, crews will be drilling from the right of way surface into the completed TBM tunnel to fill portions of the tunnels with concrete.

Hours of Work  Lire la suite »

mai 102017

Ongoing Preparatory Works between Brentcliffe Road and Midland Avenue: Street Furniture Removals SPRING & SUMMER 2017

What Work is Taking Place?

As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Brentcliffe Road and Midland Avenue. Lire la suite »

mai 092017

Shoring and Excavation Work Continues for Laird Station: Long Term Sidewalk Closure

Since June 2016, shoring and excavation work has been underway within the main and secondary entrance sites for the future Laird Station. Lire la suite »

avril 272017

Update: Material and Equipment Deliveries at Laird Station

During the week of April 24 and May 1, there will be a number of large equipment and material deliveries to the Main Entrance at Laird Station. To safely offload equipment and materials into the bottom of the shaft temporary lane and sidewalk closures will be in place as required. A mobile crane will be used to facilitate deliveries. 

 Lire la suite »