Sewer Re-lining Works at Laird Station

Sewer re-lining is a process intended to increase the durability of the sewers.  At Laird Drive and Eglinton Avenue East, local sewers will be re-lined in the vicinity of the construction sites. 

The liner is a flexible membrane that is placed inside the sewers. Lining is designed to be generally non-disruptive and eliminates the need for excavation of the entire sewer section. The required activities take approximately three days for each sewer section.  Lire la suite »

septembre 012017

Update: Dewatering System at Laird Station

Re-Issue date: September 1, 2017

The term “dewatering” means pumping from the ground water at a site where there will be excavation.  At Eglinton Avenue East and Laird Drive, dozens of small wells will be drilled along the curbside eastbound lane. Wells will be drilled and shallow trenches will be required to lay the pipes, pumps, wells and valves to do the work.  

Hours of Work/ What to Expect  Lire la suite »

août 292017

Pedestrian Safety near Construction Sites

The tunnelled section between Brentcliffe Road and Black Creek Drive is complete, and last year, construction activities began at all 15 underground stations including Kennedy Station. The preparatory works at the at-grade portion of the line, between Brentcliffe Road and Kennedy Station, also started this summer. Since the end of school, many work zones have been set up for construction and some major intersections along Eglinton Avenue have changed.

Lire la suite »

août 182017

Update: Tunnel Concrete Pour for Laird Station

To progress construction at Laird Station and prepare for upcoming mining works, crews will be drilling from the right of way surface into the completed TBM tunnel to fill portions of the tunnels with concrete.

Hours of Work  Lire la suite »

août 042017

Update: Overnight Watermain Investigations for Laird Station

What Work is Happening?

To prepare for upcoming mining works at Laird Station, a careful inspection of watermains in the area is required. 

Crews will complete water leakage detection for the watermains on Eglinton Avenue East between Sutherland Drive and Brentcliffe Road. The scope of work includes testing watermains and associated fittings on Eglinton and 10 meters north/south of Eglinton.  Lire la suite »

juillet 272017

Update: Sewer Re-lining Works at Laird Station

Sewer re-lining is a process intended to increase the durability of the sewers.  At Laird Drive and Eglinton Avenue East, local sewers will be re-lined in the vicinity of the construction sites. 

The liner is a flexible membrane that is placed inside the sewers. Lining is designed to be generally non-disruptive and eliminates the need for excavation of the entire sewer section. The required activities take approximately three days for each sewer section.  Lire la suite »

juillet 212017

Update: Gas Main Support at Laird Station

To prepare for upcoming mining operations at Laird Station, micro piles will be drilled to the north of the Laird Station Secondary entrance. Micro piles will support local gas mains during mining. 

Hours of Work/ What to Expect  Lire la suite »

juillet 132017

Laird - Leaside Construction Liaison Committee Meeting

The construction liaison committee meeting of Leaside and Laird Stations was held on July 12, 2017. You can see the presentation here:

Lire la suite »

juillet 042017

Overnight Preparatory Works for Sewer Re-lining at Laird Station

What Work is Taking Place

Sewer re-lining is a process intended to increase the durability of the sewers.  At Laird Drive and Eglinton Avenue East, local sewers will be re-lined in the vicinity of the construction sites.  Lire la suite »

juin 302017

Crane Installation at Laird Station Main Entrance

A large tower crane will be delivered and installed at the Laird Main Entrance during the week of July 3rd. 

What to Expect  Lire la suite »