Laird Drive
À la recherche de nouvelles concernant des travaux près d’une i
Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.
- Black Creek Drive
- Keele Street
- Caledonia Road
- Dufferin Street
- Oakwood Avenue
- Allen Road
- Bathurst Avenue
- Chaplin Crescent
- Avenue Road
- Yonge Street
- Mount Pleasant Road
- Bayview Avenue
- Donlea Drive/Hanna Road
- Laird Drive
- Leslie Street
- Don Mills Road
- Ferrand Drive
- Wynford Drive
- Bermondsey Road
- Victoria Park Avenue
- Pharmacy Avenue
- Lebovic Avenue
- Warden Avenue
- Birchmount Road
- Ionview Road
- Kennedy Road
- Little Blvd.
- Petman Avenue
- Brentcliffe Road
- Allen Road
- Avenue Road
- Bathurst Avenue
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Lebovic Avenue
- Leslie Street
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Wynford Drive
- Warden Avenue
- Yonge Street

Updated: Ventilation Fan Works at Laird Station
Original Issue Date: December 18, 2017
What Work is Taking Place?
Starting as soon as mid-January 2018, crews will complete electrical connections for ventilation fans within the existing tunnels underneath Eglinton Avenue. Lire la suite »
Laird - Leaside Construction Liaison Committee Meeting
The construction liaison committee meeting of Leaside and Laird Stations was held on January 10, 2018. You can see the presentation here:
Laird - Leaside Construction Liaison Committee Meeting
The construction liaison committee meeting of Leaside and Laird Stations was held on November 8, 2017. You can see the presentation here:
Laird - Leaside Construction Liaison Committee Meeting
The construction liaison committee meeting of Leaside and Laird Stations was held on October 11, 2017. You can see the presentation here: Lire la suite »
Tunnel Backfilling Brentcliffe Road to Laird Drive
What Work is Taking Place?
To support the ongoing mining works at the future Laird Station, a layer of backfill (granular material) will be added to the base of the existing tunnel from the Brentcliffe Portal to Laird Drive.
Backfill material will be stockpiled and then be pushed in to the tunnel at Brentcliffe Portal and inside the tunnels towards Laird Drive. Compaction of the material will occur inside of the tunnels. Lire la suite »
Update: Mining at Laird Station Main Entrance
Original Issue Date: September 19, 2017
Re-issue Dates: October 2, 2017 Lire la suite »
Periodic Deliveries at Laird Station into Spring 2018
What Work is Taking Place?
To support a number of large equipment and material deliveries on Eglinton Avenue East near the Main and Secondary Entrances at Laird Station periodic lane closures to accommodate deliveries will be required until Spring 2018. To safely offload equipment and materials into the bottom of the shaft temporary lane closures will be in place as required. Lire la suite »
Mining at Laird Station Main Entrance
The Eglinton Crosstown includes a 10-kilometre underground portion, between Weston Road and Laird Drive, where 15 below-grade stations are under construction. Eleven will be built using a “cut-and cover” method and four, including Laird Station, are going to be “mined.”
Excavation of the main entrance at Laird Station is complete and mining will begin soon. Lire la suite »
Laird - Leaside Construction Liaison Committee Meeting
The construction liaison committee meeting of Leaside and Laird Stations was held on September 13, 2017. You can see the presentation here: