Re-issue: Telecommunication Utilities Relocation: Birchmount Road to Treverton Drive

What Work is Taking Place?

• Crews will begin relocation of existing telecommunication lines along Eglinton Avenue East, between Birchmount Road and Treverton Drive.

• Telecommunication lines within utility chambers as well within pre-existing duct banks will be relocated in preparation for station construction.

• All work conducted during this phase will occur within the public boulevards.

Lire la suite »

juin 282017

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on June 27, 2017. You can see the presentation here:

juin 202017

Hydro Utility Relocation for the Eastern End of the Eglinton Crosstown LRT Line

What Work is Taking Place?

Crews will relocate and upgrade existing overhead hydro utilities between Birchmount Road and Kennedy Station in preparation for construction of the surface section dedicated transit lanes (guideway), the Kennedy Portal, and the Kennedy LRT Station. Existing overhead and underground hydro lines will be relocated from the north side of Eglinton Avenue East to the south side of Eglinton Avenue East.

juin 092017

Preparatory Road Works on Eglinton Avenue East for Surface Stops

Preparatory Road Works on Eglinton Avenue East for Surface Stops

The surface section of the Eglinton Crosstown LRT will run down the centre of Eglinton Avenue East in dedicated transit lanes at street level. To prepare for the construction of the surface section, crews are working to get the roadway ready.

Setting up the construction work zones in the roadway will require changes to how car and truck, bus, and pedestrian traffic flows along Eglinton Avenue East and the associated intersections where future stops will be located.  Lire la suite »

mai 312017

Pharmacy - Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of stops and station between Pharmacy and Kennedy was held on May 30, 2017. You can see the presentation here:

Lire la suite »

mai 102017

Ongoing Preparatory Works between Brentcliffe Road and Midland Avenue: Street Furniture Removals SPRING & SUMMER 2017

What Work is Taking Place?

As part of ongoing preparatory works, crews will begin the process of removing street furniture across the Eglinton Avenue East corridor between Brentcliffe Road and Midland Avenue. Lire la suite »

avril 062017

Surface Section and Kennedy Station Open House

Thank you for attending our Surface Section and Kennedy Station Open House on April 5, 2017.

For those of you who missed it, the presentation is here: