Ferrand Drive

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
décembre 182018

TRAFFIC CHANGE AT DON VALLEY PARKWAY

Last Updated: January 29, 2019

WHAT WORK IS TAKING PLACE?

As part of road widening and reconstruction works approaching and within the Don Valley Parkway and Eglinton Avenue East intersections, two new traffic stages (depicted below) will be implemented. Each stage will last approximately four (4) weeks. The first stage will be implemented as early as February 11th, 2019.  Lire la suite »

novembre 142018

Eastern Works Open House (Science Centre Station and Sunnybrook Park Stop to O'Connor Stop)

Thank you for attending the open house about Science Centre Station and Sunnybrook Park Stop to O'Connor Stop on November 13, 2018. For those of you who missed it, the presentation is here:

Lire la suite »

novembre 022018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here: Lire la suite »

octobre 042018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here:

Lire la suite »

juin 182018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for June 14, 2018. You can see the presentation here:

Lire la suite »

juin 012018

EXTENDED: Sanitary Sewer Crossing Work for Science Centre Station

What Work is Taking Place?

Crews continue to connect the new sanitary sewer to the existing sanitary sewer infrastructure, as part of infrastructure upgrade for the new Science Centre Station. Work commenced as early as Tuesday, May 22, 2018 and was estimated to take approximately two (2) weeks to complete. However, crews have encountered some unforeseen issues. Lire la suite »

mai 182018

Sanitary Sewer Crossing Work for Science Centre Station

What Work is Taking Place?

Crews will connect the new sanitary sewer to the existing sanitary sewer infrastructure, as part of infrastructure upgrade for the new Science Centre Station, beginning as early as Tuesday, May 22, 2018. Work is expected to take approximately two (2) weeks to complete* between 8:00 PM and 6:00 AM. Lire la suite »

mai 072018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The presentation for the construction liaison committee meeting of Brentcliffe - Victoria Park for the month of May 2018 can be viewed here:

Lire la suite »

avril 122018

REISSUE: LOW WATER PRESSURE NOTICE: Watermain Connection Work for Science Centre Station

What Work is Taking Place?

Crews are working to replace an existing watermain north of Eglinton Avenue East within the existing work zone at the northeast corner of Don Mills Road and Eglinton Avenue East. This work supports the upgrade of existing water infrastructure around the future Science Centre Station. Lire la suite »

avril 062018

Brentcliffe - Vctoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on April 5, 2018. You can see the presentation here:

Lire la suite »