Syndiquer le contenu
 
janvier 072019

Traffic Improvement at Don Mills Road and Eglinton Avenue East

ORIGINAL POSTING: SEPTEMBER 25, 2019

UPDATED: NOVEMBER 7, 2019 Lire la suite »

novembre 142018

Eastern Works Open House (Science Centre Station and Sunnybrook Park Stop to O'Connor Stop)

Thank you for attending the open house about Science Centre Station and Sunnybrook Park Stop to O'Connor Stop on November 13, 2018. For those of you who missed it, the presentation is here:

Lire la suite »

novembre 022018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here: Lire la suite »

octobre 152018

Traffic Changes at Don Mills and Eglinton for Science Centre Station

ORIGINAL POST: OCTOBER 5, 2018

Upcoming Traffic Changes at Don Mills and Eglinton

What Work is Taking Place? Lire la suite »

octobre 042018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for October 4, 2018. You can see the presentation here:

Lire la suite »

août 232018

UPDATE: Overnight Watermain Relocation at Science Centre Station

What Work is Taking Place?

As part of the ongoing watermain upgrades for the future Science Centre Station, crews will be conducting overnight watermain relocation works at the intersection of Eglinton Avenue East and Don Mills Road.

 In an effort to minimize disruption and to protect the safety of the local community and commuters, work will be performed overnight beginning as early as Sunday August 26, 2018 and will continue for approximately five (5) nights. Lire la suite »

juin 182018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for June 14, 2018. You can see the presentation here:

Lire la suite »

juin 122018

Hydro Duct Bank Connection Works for Science Centre Station between Wynford and Eglinton on Don Mills Road

What Work is Taking Place?

As part of ongoing utility relocation work for the future Science Centre Station, crews will be conducting hydro infrastructure work in the vicinity of the Don Mills Road and Eglinton Avenue East intersection, beginning as soon as Wednesday, June 13, 2018. Ongoing hydro infrastructure upgrades support construction of the Eglinton Crosstown LRT. Lire la suite »

juin 122018

UPDATE: Overnight Storm Water and Sanitary Utility Relocation for Science Centre Station

What Work is Taking Place?

As part of the ongoing storm water and sanitary utility upgrades for the future Science Centre Station, crews will be completing the connection of the new infrastructure to the existing at the northwest corner of Don Mills Road and Eglinton Avenue East. Lire la suite »