août 262022

Pedestrian Route Change at Chaplin Station - August 26, 2022

What Work is Taking Place?

As early as Friday, August 26, 2022, a new pedestrian route will be implemented on the north side of Eglinton Avenue between Gilgorm Road and Latimer Avenue to accommodate sidewalk construction. Pedestrians will be rerouted south around the work zone (refer to map). This configuration will remain in place for approximately two (2) weeks.

août 252022

Update: Notice of Water Shut-off NEW DATE: - Friday, August 26, 2022

What Work Is Taking Place?

On Friday, August 26, 2022, crews will perform watermain works at Chaplin Station.  A water shut-off is required to facilitate the work. The water shut-off will start as early as 8:00 a.m. for approximately eight (8) hours. Water service will be restored upon completion of the work. Please carefully read the water shut-off details below.

Water Shut-off Details:

août 222022

Update: Notice of Water Shut-off NEW DATE: Wednesday, August 24, 2022

What Work Is Taking Place?

On Wednesday, August 24, 2022, crews will perform watermain works at Chaplin Station.  A water shut-off is required to facilitate the work. The water shut-off will start as early as 8:00 a.m. for approximately eight (8) hours. Water service will be restored upon completion of the work. Please carefully read the water shut-off details below.

Water Shut-off Details:

août 222022

Closure of Latimer Avenue at Eglinton Avenue West - As early as August 29, 2022

What Work is Taking Place?

As early as Monday, August 29, 2022, Latimer Avenue will be closed at Eglinton Avenue West to facilitate road and sidewalk restoration works. The closure will remain in place for approximately two (2) weeks. Pedestrians will be rerouted north around the work zone on Latimer Avenue.  

What to Expect

août 192022

Notice of Water Shut-off - Tuesday, August 23, 2022

What Work Is Taking Place?

On Tuesday, August 23, 2022, crews will perform fire hydrant works at Chaplin Station.  A water shut-off is required to facilitate the work. The water shut-off will start as early as 8:00 a.m. for approximately eight (8) hours. Water service will be restored upon completion of the work. Please carefully read the water shut-off details below.

Water Shut-off Details:

août 182022

Notice of Water Shut-off - Monday, August 22, 2022

What Work Is Taking Place?

On Monday, August 22, 2022, crews will perform fire hydrant works at Chaplin Station.  A water shut-off is required to facilitate the work. The water shut-off will start as early as 8:00 a.m. for approximately eight (8) hours. Water service will be restored upon completion of the work. Please carefully read the water shut-off details below.

Water Shut-off Details:

août 172022

Pedestrian Route Change at Chaplin Station - August 17, 2022

What Work is Taking Place?

On Wednesday, August 17, 2022, a new pedestrian route will be implemented on the north side of Eglinton Avenue between Gilgorm Road and Chaplin Crescent to accommodate sidewalk construction. Pedestrians will be rerouted south around the work zone (refer to map). This configuration will remain in place for approximately two (2) weeks.

août 112022

Lane Shift at Chaplin Crescent and Eglinton Avenue West - As early as August 11, 2022

What Work is Taking Place?

As early as Thursday, August 11, 2022, traffic on Eglinton Avenue West will shift fully to the south side of the road. Traffic on Chaplin Crescent will remain on the west side of the road. This traffic configuration will remain in place through late Summer 2022. For more information, please review the complete notice below.

What to Expect

juillet 062022

Avenue & Chaplin CLC - Presentation Deck - July 6, 2022

intro

The Construction Liaison Committee of Avenue & Chaplin was held on July 6, 2022. You can review the presentation here: Lire la suite »