Brentcliffe Road

À la recherche de nouvelles concernant des travaux près d’une i

Choisissez une intersection dans le menu déroulant ci-dessous pour obtenir tous les renseignements et dernières nouvelles sur la construction dans cette zone. Les intersections sont indiquées d’ouest en est, Eglinton étant la principale rue perpendiculaire.

Syndiquer le contenu
 
mars 022018

Brentcliffe - Vctoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on March 1, 2018. You can see the presentation here:

Lire la suite »

février 092018

Telecommunication Relocations (Brentcliffe to Leslie)

What Work is Taking Place?

Crews will relocate and upgrade existing overhead and underground telecommunication between Brentcliffe Road and Leslie Street along Eglinton Ave East in preparation for construction of the Brentcliffe Portal and Sunnybrook Park Stop.

 Lire la suite »

février 092018

Early Morning Concrete Pours at Brentcliffe Portal 2018

What Work is Taking Place?

Crews will be pouring concrete on an ongoing basis throughout 2018 to continue building the foundation and roof slabs for the Brentcliffe Portal. Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street.

Hours of Work Lire la suite »

février 022018

Recommencement of Overnight Sanitary Sewer Relocation at Brentcliffe Portal Feb. 4th to 9th from 9pm to 5am

Original Issue Date: January 25, 2018

Eglinton Avenue East Lane Closure between Brentcliffe Road and Leslie Street

What Work is Taking Place?

Crews will complete the relocation of an existing sanitary sewer line on Eglinton Avenue East between Brentcliffe Road and Leslie Street to support the upgrade of existing infrastructure at the future Brentcliffe Portal and Sunnybrook Park Stop. Lire la suite »

janvier 252018

Recommencement of Overnight Sanitary Sewer Relocation at Brentcliffe Portal Jan. 29 to Feb. 1 from 9pm to 5am

Eglinton Avenue East Lane Closure between Brentcliffe Road and Leslie Street

What Work is Taking Place?

Crews will complete the relocation of an existing sanitary sewer line on Eglinton Avenue East between Brentcliffe Road and Leslie Street to support the upgrade of existing infrastructure at the future Brentcliffe Portal and Sunnybrook Park Stop. Lire la suite »

janvier 162018

Rescheduled: Overnight Sanitary Sewer Relocation at Brentcliffe Portal January 16th to 21st from 9:00 p.m. to 5:00 a.m.

Original Issue Date: October 24, 2017
Repost & Update Date: November 27 and December 8, 2017
Repost & Update (2) Date: January 5, 2018 and Januaey 16, 2018

Eglinton Avenue East Lane Closure between Brentcliffe Road and Leslie Street

What Work is Taking Place? Lire la suite »

janvier 122018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on January 11, 2018. You can see the presentation here:

Lire la suite »

janvier 052018

Rescheduled: Overnight Sanitary Sewer Relocation at Brentcliffe Portal January 9th to 14th from 9:00 p.m. to 5:00 a.m.

Original Issue Date: October 24, 2017
Repost & Update Date: November 27 and December 8, 2017
Repost & Update (2) Date: January 5, 2018 

Eglinton Avenue East Lane Closure between Brentcliffe Road and Leslie Street

What Work is Taking Place? Lire la suite »

décembre 082017

Cancelled: Overnight Sanitary Sewer Relocation for the Brentcliffe Portal Starting Friday, December 8 at 9:00 p.m.

Sanitary sewer relocation work on Eglinton Avenue East between Brentcliffe Road and Leslie Street has been cancelled due to weather. 


Updated: December 8, 2017
Previous Update Issued: November 27, 2017
Original Issue Date: October 24, 2017
Lire la suite »

décembre 072017

Updated: Early Morning Concrete Pours at the Brentcliffe Portal in December 2017

What Work is Taking Place?

Crews will be pouring the concrete foundation and roof slabs for the Brentcliffe Portal. Work will be conducted within the existing work zone located on Eglinton Avenue East between Brentcliffe Road and Leslie Street. Due to the large size of these concrete pours, work will start at 4:00 a.m. in order to reduce impact to traffic in the area. Lire la suite »