Pedestrian Walkway and Sidewalk Closures at Birchmount Road to Rosemount Road

 

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting curb and pedestrian walkway work on the south side of Eglinton Avenue East between Birchmount Road and Rosemount Road. Starting as early as Wednesday, October 2nd 2019, and lasting approximately three (3) weeks access to the main walkway of 2225 and 2239 Eglinton Avenue East will be temporarily restricted. Property access to the buildings will be maintained on either side of the property.  Lire la suite »

septembre 252019

Pharmacy to Kennedy Construction Liaison Committee Meeting

The construction liaison committee meeting of Pharmacy to Kennedy was held on September 24, 2019. You can see the presentation here:

 

Download the presentation

septembre 112019

Update: North Driveway Closure at 2300 Eglinton Avenue East for Work at Massey Creek

Original Post: August 28, 2019

Updated: September 11, 2019

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. Work will continue for approximately 4 months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Lire la suite »

août 272019

Update: East Bound Left Turn Temporarily Closed at Rosemount

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews  will continue work with stage 2 at Massey Creek.

Preparatory work began in late February 2019 includes tree removals, dewatering of wells and deep excavation. Crews will be excavating nine and half (9.5) meters deep and replacing the storm water culvert.

UPDATE: 

The east bound left turn will be temporarily closed as of Monday, August 26th due to utility relocation. Lire la suite »

août 232019

Overnight Water Shut off August 28, 2019 7:00 PM — 5:00 AM at Massey Creek

What Work is Taking Place?

As part of the ongoing works to replace the existing culvert at Massey Creek, crews will be upgrading and relocating wet utilities.

An overnight water shut off is required during these works.  It will occur on Wednesday August 28 from 7 p.m. – 5 a.m.

 Hours of Work Lire la suite »

août 162019

Traction Power Substation Construction Continues at Birchmount Road

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be conducting work on the Traction Power Substation (TPSS) 12, located on the north east corner of Birchmount Road and Eglinton Avenue East intersection. Starting as early as August 23, 2019 and lasting for approximately one (1) week. 

The north sidewalk on Eglinton Avenue East will remain closed in order to carry out the work safely. Lire la suite »

juillet 102019

Update: Eastbound Left Turn Reinstated at Rosemount Drive at Eglinton Avenue East

What Work is Taking Place?

As part of the ongoing works to build the LRT system along Eglinton Avenue East, crews will be replacing the existing culvert at Massey Creek. Work began as early as late February 2019 and will last for approximately nine (9) months. The creek is located at the signalized intersection of Eglinton Avenue East and Rosemount Drive. Lire la suite »

juin 192019

Guideway Work at Birchmount Road

Guideway Work Birchmount Road

What Work is Taking Place?

  

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be continuing guideway work in the center of Eglinton Avenue East. As early as July 1, 2019 the construction zone will shift to the centre of Eglinton Avenue East at Birchmount Road and be in place for approximately six (6) weeks. Lire la suite »

juin 132019

Weekend Traffic Restrictions at Birchmount Road

Latest Update: July 5, 2019

What Work is Taking Place?

The north side pavement reconstruction works at Eglinton Avenue East and Birchmount Road will be moved to July 6/7 (from June 29/30). The guideway work in the centre of Eglinton Avenue East will now be in place as July 8th.

Hours of Work Lire la suite »