mars 042019

New Traffic Configuration: Eglinton Avenue East at Jonesville Crescent

WHAT WORK IS TAKING PLACE?

As utility installations progress along Eglinton Avenue East between Bermondsey Road and Victoria Park Avenue, four (4) new traffic stages will be implemented at Jonesville Crescent to accommodate the work zones (depicted below). Traffic will shift to the first stage as early as Monday, March 4th, 2019. Each stage will last approximately one (1) week. Lire la suite »

février 272019

East At-Grade Town Hall Meeting

Our town halls provide information on construction impacts on Eglinton Avenue East between Credit Union Drive to Ionview Road feature detailed project maps and imagery. You can see the presentation here:

Lire la suite »

février 212019

Temporary Crosswalk Closure at Credit Union Drive

Temporary Crosswalk Closure at Credit Union Drive

WHAT WORK IS TAKING PLACE? Lire la suite »

février 192019

New Traffic Configuration: Wilson Brook Culvert East of Sloane Avenue

ORIGINAL POSTING: FEBRUARY 1, 2019

WHAT WORK IS TAKING PLACE?

Work on the Wilson Brook Culvert has been underway since late August 2018 on Eglinton Avenue East. Crews are building a temporary storm drain line, as well as excavating and replacing the storm water culvert under Eglinton Ave East. 

février 152019
janvier 112019

New Traffic Configuration: Eglinton Avenue East between Sloane Avenue and Victoria Park Avenue

Last Updated: January 14, 2019

WHAT WORK IS TAKING PLACE?

As part of utility relocations, road widening and road reconstruction along Eglinton Avenue East between Sloane Avenue and Victoria Park Avenue, new traffic staging (depicted below) will be implemented as early as January 15, 2019. This traffic configuration will be in place for up to four (4) weeks.

All works are in support of the construction of the Crosstown LRT tracks and guideway (dedicated transit lane) in the centre of Eglinton Avenue East. Lire la suite »

décembre 062018

Updated: Road Reconstruction at Credit Union

Last Updated: February 5, 2019

WHAT WORK IS TAKING PLACE?

Crews will be conducting roadway surface reconstruction approaching and within the Swift and Credit Union Drive intersection along Eglinton Avenue East. Work will begin as early as November 21, 2018 on the south side of Eglinton at Credit Union Drive and then shift to the north side of Eglinton Avenue East at Swift Drive late-February, 2019. A separate notice will be issued for the closure of Swift Drive.   Lire la suite »

novembre 142018

Eastern Works Open House (Science Centre Station and Sunnybrook Park Stop to O'Connor Stop)

Thank you for attending the open house about Science Centre Station and Sunnybrook Park Stop to O'Connor Stop on November 13, 2018. For those of you who missed it, the presentation is here:

Lire la suite »

novembre 132018

Road Reconstruction at Credit Union and Swift Drive

What Work is Taking Place?

Crews will be conducting roadway surface reconstruction approaching and within the Swift and Credit Union Drive intersection along Eglinton Avenue East. The reconstruction follows the completion of utilities work in this area. Lire la suite »